West Shore Lake Pontchartrain Project
The West Shore Lake Pontchartrain Hurricane Protection project is an 18.5-mile system that includes 17.5 miles of levees, one mile of T-wall, drainage structures, pump stations, and several non-structural protection measures to form an integrated protection system.
The West Shore Pontchartrain Project alongside the US Army Corps of Engineers, New Orleans District. consists of clearing, grubbing, excavating new drainage canals, placing culverts and drainage structures, building new T-walls and levee ramp crossings, placing levee embankments, geotextile work, turf establishment, and surfacing.
Myrtle Grove Project
US Army Corps of Engineers, Vicksburg District, has awarded Greenup Cajun JV, LLC a $102.5 million dollar construction contract to build hurricane protection structures and move levees and drainage canals in Louisiana’s Plaquemines Parish.
Greenup Cajun JV, LLC, presented the lowest bid of four for the “New Orleans to Venice 1st lift levee and drainage canal relocation project, La Reussite to Myrtle Grove, Plaquemines Parish.” The project will consist of clearing, grubbing, excavating new drainage canals, placing culverts and drainage structures, building new T-walls and levee ramp crossings, placing levee embankments, geotextile work, turf establishment, and surfacing. The estimated cost of the project is $102,452,461.00.
Water Meter Project
St. John the Baptist Parish (St. Joahn) is now in possession of some well-needed water meter upgrades thanks to the efforts of Greenup Industries Inc. (Greenup) with partner Aclara Technology. Greenup was awarded a $5.27 million contract from the Louisiana Parish in December 2019 to install 16,491 residential smart water meters, 382 commercial meters, and 10 fire hydrant meters.
Greenup reports that installation on 15,000 residential and commercial smart water meters were completed despite numerous setbacks (COVID, 2020's most active Hurricane Season since 2005, Global Supply Chain Impacts, Hurricane Ida causing extensive damage to LaPlace and damaging some of the installed equipment). St. John Parish officials issued a resolution on March 28 to issue a Change Order on the existing contract and have the remaining 2,600 meters installed at a later date.
The new smart water meters feature more accurate leak detection and improved residential and commercial services. Residents can use a Customer Portal on their computer or mobile device for utility maintenance, such as setting up alerts for their water consumption, monitoring leak detection in real-time, and viewing live data to keep their water bill down. The water meters are networked into the St. John Parish data management system, allowing the parish to bill customers more accurately and monitor any potential infrastructure issues.