hurricane protection

MYRTLE GROOVE LEVEE construction PROJECT update

The U.S. Army Corps of Engineers is continuing to make progress with the New Orleans to Venice (NOV) Hurricane Protection project in Plaquemines Parish, La. The purpose of the NOV project is to provide an improved levee system for storm risk reduction for Plaquemines Parish by repairing and restoring the original project levees, accelerating the completion of unconstructed portions of the authorized project, and armoring critical elements of the authorized project. The NOV federal levees are located on the east bank of Plaquemines from Phoenix to Bohemia and on the west bank from St. Jude to Venice.

Currently, along the La Reussite to Myrtle Grove levee reach, USACE is constructing approximately seven miles of new drainage canals and levees. USACE workers and their construction partners are placing embankment material at the site of the levee construction, slowly building up layers of soil and material for the levee. So far, 85% of the canal have been completed and approximately 50% of the levee has been built along this particular levee reach. This portion of the project is scheduled to be completed by calendar year 2026.

February construction Project Updates

Stockpile 1 - Progress has been severely impacted by rain every few days.  When weather permits, we are working our haul roads in the Spillway and the stockpile location in LaPlace.  We are also continuing to excavate material allowing it to begin the drying process, because the material that is excavated is very wet.  As a result of the weather, we are currently scheduled to complete this project in the early fall of 2023.

Myrtle Grove - This project continues to progress quickly and is ahead of schedule.  So far we have placed 74,000 square yards of separator fabric under access roads, 55,000 Cubic Yards of sand for those access roads and preload location, excavated over 230,000 cubic yards of material for the drainage canal, placed 76,000 square yards of Levee Support Geotextile, and built 170,000 cubic yards of clay levee.

This project is scheduled to be completed in the summer of 2025 but we anticipate a change request from the Corps of Engineers that will significantly extend the execution period.  

About Greenup Industries

Based in Kenner, Greenup Industries offers contracting and specialized construction services for industrial, commercial, and municipal clients. The company's proprietary software, the Greenup Tracker, can connect third-party vendors with facilities that need painters, plumbers, groundskeepers, carpenters, etc.

If you would like more information on this project, please contact Greenup Industries at 225.283.4843 or info@greenupind.com.

Rodney Greenup

Greenup Industries 

+1 225-383-4843

Updates on Two of Our Projects with USACE

Despite some setbacks from weather, our work with the U.S. Army Corps of Engineers on the West Shore Lake Pontchartrain Project (WSLPP) has seen significant progress in the past few months. Greenup's primary role has been excavating, processing, and stockpiling clay in two piles within the Bonnet Carre Spillway. By the end of the project, an estimated 1.5 million cubic yard of clay will be removed from the Spillway.

Construction manager Steven Keen provided these updates on the two stockpile sites:

"Stockpile 2 - PROJECT IS COMPLETE! Final testing of materials, coring samples of the stockpile, and as-builts are all that remain on this project. This is a major milestone as it was Greenup's first Corps of Engineers project of what is now three in total.

Stockpile 1 - This project is continuing to ramp up production, but stockpiling of clay is being hampered by rain. We are continuing to haul clay when the weather permits. We are also working on days we can't haul by excavating clay from the borrow pit in the Spillway and processing the material (allowing it to air dry). We are also improving the haul roads in the spillway and at the stockpile location in LaPlace. This project should be complete in mid-late spring of 2023."  

Keen also reported progress on the La Reussite to Myrtle Grove Levee Plaquemines Parish project, a joint venture with Cajun Industries alongside the U.S. Army Corps of Engineers. The project is a fixed-price construction contract to build hurricane protection structures and move levees and drainage canals in the New Orleans area. 

"This large (4 mile long) project, over $100M, is moving out very quickly," Keen said, "We have already built, or improved, 8,000 LF of access roads so that equipment can safely access the project site, cleared vegetation from over half of the project footprint, excavated 100,000 CY of material for the drainage canal, and built over 100 LF of concrete pipe culverts to facilitate drainage. This project is ahead of the required completion date of June 2025."

Greenup Industries provides a full range of onboarding solutions, maintenance, design, and specialty construction services to our diverse clients. We offer effective onboarding, reduced costs, accountability, and consistent vetting of vendors. Greenup Industries has clocked over 500,000 plus safe work man-hours and is the recipient of several awards for safety, including the Gold Medal Award, presented by Shell/Norco, the Contractor Safety Award, presented by CAST, and the Safety Excellence Award, presented by Gulf South Safety Council. To learn more about the benefits of having Greenup Industries work for you, please contact us today by calling (225) 283-4843 or visiting us online at www.greenupind.com.